Back to the Map

Abu Sultan Electric Power Plant

 

East Delta Electricity Production Co .

Co .

4 units of steam turbines , Each of 150 M.W, All of 600 M.W Installed  Capacity  Dual Firing (Mazzot , NG) , Commercial operation date 1983-84-86 .

Description

3678

·   Generated  Energy ( G.W.h )

Statistics  2012/2013

3404

·   Transmitted  Energy ( G.W.h )

259.5

·   Fuel Consumption (gm / KWh )

580

·   Peak Load ( M.W)

72

·   Load Factor ( % )

70

·    Capacity  Factor ( % )

33.8

·    Thermal Efficiency ( % )

87.4

·    Availability  ( % )