Sidi Krir Electric Power Plant

 

West Delta  Electricity  Production Co .

Co .

2 units of steam turbines , Each Of 320 M.W Installed  Capacity ,  Dual Firing ( Mazzot , NG ), Commissioned 1999-2000 .

Sidi Krir 1,2

 

Description

2 units of Steam turbines , Each of 341.25 M.W Installed  Capacity , Dual Firing ( Mazzot , NG ) , Commissioned 2002, BOOT .

Sidi Krir 3,4

 

2 units of gas turbines , Each of  250 M.W
 +*One steam turbine of 250M.W), with total Installed Capacity of 500 M.W
,  Dual Firing( Solar , NG ), Commissioned 2009.

* steam turbine is still under construction .

 

Sidi Krir Cc

Sidi Krir Cc

Sidi Krir 3,4

Sidi Krir 1,2

·   Generated  Energy

      ( G .W. h )

Statistics  2009/2010

 

3140

4759

4527.3

3080.3

N.A

4367

·   Transmitted  Energy 

    ( G .W. h )

238.7

N.A

210.7

·   Fuel Consumption

    ( g.m / K.W.h )

530

N.A

667

·   Peak Load ( M.W )

68

N.A

77

·   Load Factor ( % )

72

N.A

81

·    Capacity  Factor

      ( % )

36.7

N.A

41.6

·    Thermal Efficiency 

      ( % )

98

N.A

98

·    Availability  ( % )

--

--

--

1995 / 1996

Generated Energy  

  (G .W. h )

--

--

--

1996 / 1997

--

--

--

1997 / 1998

--

--

--

1998 / 1999

--

--

1206

1999 / 2000

--

--

3363

2000 / 2001

--

2441

3820

2001 / 2002

--

4469

3742

2002 / 2003

--

4821

3872

2003 / 2004

--

4749

3974

2004/2005

--

4847

3548

2005/2006

--

4574

3758.426

2006/2007

--

4582

4166

2007/2008

25

4908

4003

2008/2009

3140

4759

4527.3

2009/2010