The Expansion plan of the Hydro Power Plants

§        The EEHC and the Hydro Power Plants Executive Authority are coordinating the planning, the preparation of the feasibility study and the following- up, and      the execution of the Hydro- Plants.

§        In 1985, the Hydro Power plant of Aswan 2, with installed capacity of 4x67.5M.W constructed.

§        In 1994 the Hydro Power plant of Esna Barrage with installed capacity of 6x14.5M.W has been constructed.

§        In 1997, the Hydro Power plant of Naga Hamadi which had a small capacity of 3x1.5M.W was rehabilitated. The station was constructed in 1942 and worked until 1971. The new plant had costed 35 million Egyptian pounds.

§        In April 2003, a Hydro Power plant was constructed in El-lahoun/ Fayoum. The plant is consists of two units with a capacity of 800K.W.

The expansion Plan in the hydro plants projects

Project

Constructing

Status

Complex Capacity M.W

Expected termination date

The new Naga hamadi hydro Power plant

Under

Construction

64

February 2008

Technical and Economical feasibility study to construct a plant on Zefta Barrage

Studies

5.5

The studies have been completed and it is expected to start execution of the project in 2006

A technical and economical feasibility study is being worked on in cooperation with the Ministry of Irrigation to construct a plant in Assuit Barrage

Studies

32

November,2005

Demitta Hydro Power plant in Kanater Delta- Damietta

Under construction (design stage)

13

December,2009

Total

 

114.5

 

 