El Tebbin Electric Power Plant

 

Cairo Electricity  Production Co .

Co .

  3  units of steam turbines ,15 MW Installed  Capacity , Duel Firing ( Ex.Gas-Mazzot ), Commissioned by 1958-59 (this station was terminated in 8/6/2005).

 El Tebbin (St)

Description

 2 units Of Gas turbines Each of 23 MW Installed  Capacity ,  Dual Firing ( Solar , NG ) , Commissioned 1979 .

El Tebbin  (G)

El Tebbin (G)

 El Tebbin (St)

 

·   Generated  Energy

     ( G W h )

Statistics  2004/2005

36.838

202.139

36.838

185.814

·   Transmitted  Energy

     ( G W h )

369.5

393.8

·   Fuel Consumption

     ( gm / KWh )

38

38

·   Peak Load ( M W )

11

61

·   Load Factor ( % )

9

50

·    Capacity  Factor

     ( % )

23.7

22.3

·    Thermal Efficiency

       ( % )

--

96.6

·    Availability  ( % )

90

248

1995 / 1996

Generated Energy     (GW h)

93.5

236

1996 / 1997

37

241

1997 / 1998

73

259

1998 / 1999

53

244

1999 / 2000

10

232

2000 / 2001

7

111

2001 / 2002

34

257

2002 / 2003

8

121

2003 / 2004

36.838

202.139

2004/2005